Prima — Operating Procedure Library · A4 · 8pp · Draft v0.1
DRAFT
Draft
Part ofPetroCompute
Operating Procedure Library
Procedure register,
revision control and
approval authority

The controlled register of every method, standard and emergency procedure the KOM Oman AI Factory operates to — with the numbering scheme, version states, approval authority and review cycle that keep it current.

Document
PRM-OPS-2026-001
Version
0.1 — Draft
Classification
Internal — controlled
Owner
COO
Applies to
KOM Muscat
72
Procedures in the
controlled register
3
Classes — MOP,
SOP and EOP
25
Drafted to 0.2,
under review
12mo
Maximum interval
between reviews
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled01 / 08
DRAFT
PRIMA
Operating Procedure LibraryPRM-OPS-2026-001 · 02 / 08
01Purpose, scope and the three procedure classes

Availability is produced by procedure, not by talent. This document is the controlled register of every procedure the Facility operates to, together with the scheme that governs how those procedures are written, approved, issued and retired. It is the index a reviewer samples from and the control record that shows the library is maintained rather than merely written once.

Scope is the KOM Oman AI Factory at Knowledge Oasis Muscat: the electrical chain from utility intake to rack, the cooling plant and secondary loops, the network fabric, the compute platform, the data halls and the security estate. Procedures owned by the customer for their own workloads sit outside this register.

MOP

Method of Procedure. A scripted, step-by-step method for planned work on live infrastructure — where a wrong step can interrupt service. Written against a specific installed model, with a defined pre-condition, abort point and rollback.

31 procedures · planned work
SOP

Standard Operating Procedure. A repeatable routine performed the same way every time — handover, installation, rounds, provisioning, records. Written for consistency and for evidence that the routine happened.

24 procedures · routine
EOP

Emergency Operating Procedure. The action to take when a system has already failed. Written to be executed under pressure by whoever is on shift, without escalation delay and without judgement calls.

17 procedures · abnormal
1.1 Why the register is the deliverable at this stage

A MOP is written against the equipment actually installed — the UPS model, the chiller make, the switchgear arrangement, the OEM's own service documentation. Writing one before the equipment is delivered produces a document that has to be discarded. The register therefore schedules each MOP to the commissioning of the system it governs, and the honest position today is that no procedure is yet approved at 1.0 because no system is yet energised.

What does exist is the register itself, the numbering and version scheme, the approval authority, and 25 procedures drafted to 0.2 — the emergency set and the core operating routines, both of which must be in place before commissioning rather than after it. Sequencing is set out at 2.4.

SamplingA reviewer sampling this library should draw from the Status column and ask for the current revision of what is marked drafted. Anything marked scheduled does not exist yet, and is shown with its target so the gap is visible rather than implied.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled02 / 08
DRAFT
PRIMA
Operating Procedure LibraryPRM-OPS-2026-001 · 03 / 08
02Numbering, version states and review cycleOne scheme, no exceptions

Every procedure carries a permanent reference and a version that changes on every release. A document without both is not controlled and must not be used at the point of work.

2.1 Reference structure
FormatPRM-<CLASS>-<DISCIPLINE>-<NNN> — for example PRM-MOP-ELE-002, the second electrical Method of Procedure.
ClassMOP, SOP or EOP as defined at section 01.
DisciplineELE electrical · MEC mechanical · NET fabric · PLT platform · OPS operations · SEC security · ENV environmental · REC records · PWR, COL, LSS, CYB for emergency classes.
SequenceAllocated once and never reused — a withdrawn procedure keeps its number.
2.2 Version states
StateVersionMeaning and permitted use
Draft0.1 – 0.9Under authoring or review. Must not be used for work on live infrastructure.
Approved1.0 and aboveReleased. The only state in which a procedure may be executed.
Revised — editorial+0.1Corrections that do not change a step. Approved by the owner alone.
Revised — technical+1.0Any change to a step, sequence, tool, tolerance or abort condition. Full approval path at section 03.
SupersededReplaced by a later version. Retained as evidence, watermarked, withdrawn from circulation.
WithdrawnThe system or activity no longer exists. Retained as a record.
2.3 Review triggers

Reviewed on the earliest of the following. Review is recorded even where nothing changes, so a current review date always exists.

  • Twelve months from the last approval or recorded review — the maximum interval, applied to every procedure.
  • On change to the governed system — equipment, firmware, software, topology, or the OEM service instruction.
  • After any execution that did not go as written — an abort, a deviation, or a step found wrong or ambiguous in use.
  • After any incident in which it was used, whether or not it contributed — under the root-cause process in PRM-IRP-2026-001.
  • On a finding from internal audit, external audit or a certification body.
2.4 Approval sequencing to service readiness
MilestoneScopeRationale
Sep 2026EOP set — 17Approved and drilled before systems are energised for commissioning, not after.
Oct 2026SOP set — 24In force from the first day the resident team is on shift.
Nov 2026MOP — electrical and mechanical, 23Written against installed plant once switchgear and cooling are energised.
Dec 2026MOP — fabric and platform, 8Written against the built cluster, approved at ready-for-service.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled03 / 08
DRAFT
PRIMA
Operating Procedure LibraryPRM-OPS-2026-001 · 04 / 08
03Authoring, review and approval authorityNamed, not delegated

A procedure is approved by a named office, not by a function. Approval is recorded against the person holding that office on the date of release, and cannot be delegated to the author.

ClassAuthored byTechnical reviewApproved by
MOPplanned workDiscipline engineer, against the OEM service instruction and the as-built drawingFacilities Manager or Engineering Manager, plus the OEM where the work affects warrantyOperations Manager; and the COO where the work touches the critical path
SOProutineFunction owner or a nominated senior engineerPeer in the same discipline, plus CISO for anything touching access or mediaFunction owner — Operations Manager, Engineering Manager or CISO
EOPemergencyFacilities Manager or Engineering ManagerOperations Manager and NOC Manager, tested in a tabletop walkthroughCOO; and the CTO for platform and cyber emergency procedures
3.1 What every procedure must contain

A document that does not carry all of the following is not accepted into the register, regardless of how sound its content is.

  1. Reference, version, approval date and next review date on the first page.
  2. Scope and the specific equipment it applies to, by make, model and asset reference — a MOP that names only a system type is rejected.
  3. Pre-conditions and permits — system state, redundancy required, isolations in place, permits obtained, customer notice given where the Demarcation Matrix requires it.
  4. Numbered steps in the order performed, each with the expected result, so that a step can be signed off individually.
  5. Abort criteria and rollback — the condition under which work stops, and the sequence that returns the system to its pre-work state.
  6. Risk to service — stated plainly, with the redundancy relied upon and the consequence of losing it during the work.
  7. Competence required — the certifications from PRM-HR-2026-001 that the executing engineer must hold.
  8. Sign-off block — executed by, verified by, returned to service by, with timestamps.
04Release, distribution and use at the point of work

Control is worthless if a superseded copy remains in circulation. The library has one source of record, and any copy taken from it is treated as uncontrolled from the moment it is printed.

Source of recordA single controlled repository. The version in the repository is the only version in force; no other copy has standing.
ReleaseOn approval, the new version is published, the prior version is watermarked superseded and removed from circulation, and the register is updated the same day.
Printed copiesPermitted for use at the point of work, marked with the version and the date printed, and destroyed at the end of the task. A printed procedure is never filed for reuse.
Verification before useThe executing engineer confirms the version against the repository before starting. This step is itself a step in every MOP.
RetentionSuperseded versions and completed sign-off records are retained for the evidence period under PRM-SOP-REC-003 and are available to audit.
AccessRead access for the resident team by discipline; write and release access restricted to the approving offices at section 03.
DisciplineWork does not proceed on a draft, on an unversioned document, or from memory. Where no approved procedure exists for a task on live infrastructure, the task is not performed until one is written and approved — or, if the situation is an emergency, it is handled under the applicable EOP and the gap is raised as a finding.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled04 / 08
DRAFT
PRIMA
Operating Procedure LibraryPRM-OPS-2026-001 · 05 / 08
05Register — Methods of Procedure31 procedures

Planned work on live infrastructure. Each MOP is written against the installed model and its OEM service instruction, and is scheduled to the commissioning of the system it governs — see 2.4.

ReferenceProcedureOwnerStatusTarget
MOP — Electrical · 12 procedures
PRM-MOP-ELE-001UPS module removal and replacementFacilities MgrScheduledNov 2026
PRM-MOP-ELE-002UPS battery string replacement and commissioningFacilities MgrScheduledNov 2026
PRM-MOP-ELE-003UPS transfer to bypass and return to normalFacilities MgrScheduledNov 2026
PRM-MOP-ELE-004Generator on-load test and return to standbyFacilities MgrScheduledNov 2026
PRM-MOP-ELE-005Generator load-bank testFacilities MgrScheduledNov 2026
PRM-MOP-ELE-006Automatic transfer switch exercise and transfer testFacilities MgrScheduledNov 2026
PRM-MOP-ELE-007Circuit breaker racking in and racking outFacilities MgrScheduledNov 2026
PRM-MOP-ELE-008Switchgear inspection and thermographic surveyFacilities MgrScheduledNov 2026
PRM-MOP-ELE-009Transformer inspection and oil samplingFacilities MgrScheduledNov 2026
PRM-MOP-ELE-010Rack PDU replacement on a live A/B feedFacilities MgrScheduledNov 2026
PRM-MOP-ELE-011Busway tap-off installationFacilities MgrScheduledNov 2026
PRM-MOP-ELE-012EPMS meter and current transformer replacementFacilities MgrScheduledNov 2026
MOP — Mechanical and cooling · 11 procedures
PRM-MOP-MEC-001Chiller isolation and return to serviceFacilities MgrScheduledNov 2026
PRM-MOP-MEC-002Chiller compressor serviceFacilities MgrScheduledNov 2026
PRM-MOP-MEC-003CRAH filter replacementFacilities MgrScheduledNov 2026
PRM-MOP-MEC-004CRAH fan and motor replacementFacilities MgrScheduledNov 2026
PRM-MOP-MEC-005CDU pump replacement on a live loopFacilities MgrScheduledNov 2026
PRM-MOP-MEC-006CDU isolation and rack loop drainFacilities MgrScheduledNov 2026
PRM-MOP-MEC-007Secondary loop fill, purge and pressure testFacilities MgrScheduledNov 2026
PRM-MOP-MEC-008Coolant chemistry sampling and adjustmentFacilities MgrScheduledNov 2026
PRM-MOP-MEC-009Valve replacement on a live secondary loopFacilities MgrScheduledNov 2026
PRM-MOP-MEC-010Dry cooler cleaning and serviceFacilities MgrScheduledNov 2026
PRM-MOP-MEC-011Make-up water system serviceFacilities MgrScheduledNov 2026
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled05 / 08
DRAFT
PRIMA
Operating Procedure LibraryPRM-OPS-2026-001 · 06 / 08
05Register — Methods of Procedure, continuedFabric and platform
ReferenceProcedureOwnerStatusTarget
MOP — Network fabric · 4 procedures
PRM-MOP-NET-001Leaf switch replacementNetwork MgrScheduledDec 2026
PRM-MOP-NET-002Spine switch firmware upgradeNetwork MgrScheduledDec 2026
PRM-MOP-NET-003Optics and cable replacement in a live fabricNetwork MgrScheduledDec 2026
PRM-MOP-NET-004Fabric re-cable for capacity additionNetwork MgrScheduledDec 2026
MOP — Compute platform · 4 procedures
PRM-MOP-PLT-001GPU node firmware and BIOS updateEng ManagerScheduledDec 2026
PRM-MOP-PLT-002Scheduler upgrade under rolling drainEng ManagerScheduledDec 2026
PRM-MOP-PLT-003Storage node replacementEng ManagerScheduledDec 2026
PRM-MOP-PLT-004Cluster software patching under rolling drainEng ManagerScheduledDec 2026
06Register — Standard Operating Procedures24 procedures

Repeatable routines performed the same way on every shift. Approved before the resident team takes occupancy, so that the first day of operation is already evidenced.

ReferenceProcedureOwnerStatusTarget
SOP — Data-hall operations · 12 procedures
PRM-SOP-OPS-001Shift handover and turnover logOps ManagerDraft 0.2Oct 2026
PRM-SOP-OPS-002Rack delivery, placement and commissioningOps ManagerScheduledOct 2026
PRM-SOP-OPS-003Server installation and asset registrationOps ManagerScheduledOct 2026
PRM-SOP-OPS-004Server decommission and removalOps ManagerScheduledOct 2026
PRM-SOP-OPS-005Drive replacement and media handlingOps ManagerDraft 0.2Oct 2026
PRM-SOP-OPS-006Smart-hands request intake and executionOps ManagerDraft 0.2Oct 2026
PRM-SOP-OPS-007Environmental round and reading logOps ManagerDraft 0.2Oct 2026
PRM-SOP-OPS-008Preventive maintenance execution and sign-offOps ManagerScheduledOct 2026
PRM-SOP-OPS-009Spares issue, return and replenishmentOps ManagerScheduledOct 2026
PRM-SOP-OPS-010Incident logging and initial triageOps ManagerDraft 0.2Oct 2026
PRM-SOP-OPS-011Change request raising and schedulingOps ManagerDraft 0.2Oct 2026
PRM-SOP-OPS-012Asset and capacity record updateOps ManagerScheduledOct 2026
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled06 / 08
DRAFT
PRIMA
Operating Procedure LibraryPRM-OPS-2026-001 · 07 / 08
06Register — Standard Operating Procedures, continuedSecurity, environmental, records
ReferenceProcedureOwnerStatusTarget
SOP — Security · 6 procedures
PRM-SOP-SEC-001Access request, approval and provisioningCISODraft 0.2Oct 2026
PRM-SOP-SEC-002Visitor registration and escortCISODraft 0.2Oct 2026
PRM-SOP-SEC-003Contractor induction and supervisionCISOScheduledOct 2026
PRM-SOP-SEC-004Access recertification cycleCISOScheduledOct 2026
PRM-SOP-SEC-005Media sanitisation and destruction witnessCISODraft 0.2Oct 2026
PRM-SOP-SEC-006Video export for a lawful requestCISODraft 0.2Oct 2026
SOP — Environmental · 3 procedures
PRM-SOP-ENV-001Water quality sampling and reportingFacilities MgrScheduledOct 2026
PRM-SOP-ENV-002Waste and e-waste consignmentFacilities MgrScheduledOct 2026
PRM-SOP-ENV-003Fuel delivery, sampling and polishingFacilities MgrScheduledOct 2026
SOP — Records and reporting · 3 procedures
PRM-SOP-REC-001Document control and revision releaseOps ManagerDraft 0.2Oct 2026
PRM-SOP-REC-002Monthly service report productionOps ManagerDraft 0.2Oct 2026
PRM-SOP-REC-003Evidence retention and retrievalOps ManagerScheduledOct 2026
07Register — Emergency Operating Procedures17 procedures

Action after a system has already failed. Written to be executed by whoever is on shift without waiting for escalation, and drilled before commissioning rather than after it.

ReferenceProcedureOwnerStatusTarget
EOP — Power · 6 procedures
PRM-EOP-PWR-001Utility supply failure and generator startCOODraft 0.2Sep 2026
PRM-EOP-PWR-002Generator fails to start on demandCOODraft 0.2Sep 2026
PRM-EOP-PWR-003UPS on battery — load transfer and shedCOODraft 0.2Sep 2026
PRM-EOP-PWR-004Loss of one power path, A or BCOODraft 0.2Sep 2026
PRM-EOP-PWR-005Total loss of power — black-building recoveryCOODraft 0.2Sep 2026
PRM-EOP-PWR-006Uncontrolled EPO activationCOOScheduledSep 2026
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled07 / 08
DRAFT
PRIMA
Operating Procedure LibraryPRM-OPS-2026-001 · 08 / 08
07Register — Emergency Operating Procedures, continuedCooling, life safety, cyber
ReferenceProcedureOwnerStatusTarget
EOP — Cooling · 5 procedures
PRM-EOP-COL-001Chiller plant total failureCOODraft 0.2Sep 2026
PRM-EOP-COL-002Coolant leak inside a data hallCOODraft 0.2Sep 2026
PRM-EOP-COL-003Temperature excursion beyond the committed envelopeCOODraft 0.2Sep 2026
PRM-EOP-COL-004Loss of make-up waterCOOScheduledSep 2026
PRM-EOP-COL-005Loss of secondary loop pressureCOOScheduledSep 2026
EOP — Life safety and security · 4 procedures
PRM-EOP-LSS-001Fire alarm and suppression releaseCOO · CISODraft 0.2Sep 2026
PRM-EOP-LSS-002Water detection under floor or in hallCOO · CISOScheduledSep 2026
PRM-EOP-LSS-003Site evacuation and roll callCOO · CISODraft 0.2Sep 2026
PRM-EOP-LSS-004Forced entry or perimeter breachCOO · CISODraft 0.2Sep 2026
EOP — Cyber · 2 procedures
PRM-EOP-CYB-001OT network isolation on a cyber eventCISO · CTODraft 0.2Sep 2026
PRM-EOP-CYB-002Emergency credential revocationCISO · CTODraft 0.2Sep 2026
08Competence, drills and audit of the library

A library is only as good as the evidence that the shift can execute it. Three controls close the loop.

Competence

Every procedure names the certifications required to execute it, from the matrix in PRM-HR-2026-001. An engineer without them does not execute it — the control is the sign-off block, not the access platform.

Cross-referenced per procedure
Drills

Every EOP is walked through on approval and exercised live at least annually, on load where the design permits. A drill that finds an unworkable step triggers a technical revision, not a note.

Annual, per emergency procedure
Audit

Audited quarterly against three tests: nothing past its review date, no superseded copy in circulation, no live-work task without an approved procedure. Findings tracked to closure.

Quarterly · Ops Manager and CISO
8.1 Register health measures
MeasureTargetReported
Procedures within review date100%Monthly
EOPs exercised in the last 12 months100%Quarterly
Executions completed as written≥ 95%Monthly
Revisions closed within 20 business days≥ 90%Quarterly
Live-work tasks without an approved procedure0Monthly
RelatedPRM-IRP-2026-001 · PRM-HR-2026-001 · PRM-SEC-2026-001 · PRM-DEM-2026-001 · PRM-ORG-2026-001.
Office of the COO

For the current revision of any procedure, the approval record, or the drill and audit history. Procedures are released only from the controlled repository.