Commissioning & Drill Programme
Five commissioning
gates and the drill
regime
behind them

How the Facility is proven before it carries load, and how the emergency procedures are exercised thereafter — the gate ladder from factory test to integrated systems test, the acceptance criteria at each gate, the witness and sign-off regime, and the twelve-month drill calendar.

Document
PRM-CDP-2026-001
Version
0.1 — Draft
Classification
Internal — controlled
Owner
COO
Applies to
KOM Muscat
5
Commissioning levels,
each a hard gate
17
Emergency procedures
under exercise
100%
EOPs exercised in
any 12 months
Dec26
Ready for service,
gate L5 cleared
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled01 / 11
DRAFT
PRIMA
Commissioning & Drill ProgrammePRM-CDP-2026-001 · 02 / 11
01Purpose, scope and what this document is not

A facility is not available because it was designed to be. It is available because each system was proven in isolation, then proven together, then proven again under fault — and because the people on shift have executed the failure procedures before the failure arrives. This document sets out both halves of that: the commissioning gate ladder that admits the Facility to service, and the drill programme that keeps the emergency procedures live once it is in service.

Scope is the KOM Oman AI Factory at Knowledge Oasis Muscat — the electrical chain from utility intake to rack, the cooling plant and secondary loops, fire detection and suppression, the security estate, the network fabric and the compute platform. Ready for service is December 2026, and gate L5 is the condition of it.

1.1 What this document is
  • The definition of each gate — what is tested, against what standard, and the criterion that constitutes a pass rather than an opinion.
  • The witness and sign-off regime — who must be present, who signs, and what the customer is entitled to attend.
  • The drill calendar — which of the 17 emergency procedures is exercised when, at what depth, and to what pass criterion.
  • The evidence set each gate and each drill produces, and how long it is retained.
1.2 What this document is not

It is not the test scripts themselves, and it is not a record of tests performed. The scripts are produced by the appointed commissioning agent against the installed plant and the manufacturers' own acceptance procedures; the records accrue as the gates are cleared. Nothing in this document should be read as evidence that a system has been tested.

Honest positionAs at issue, no gate has been cleared and no drill has been performed — no system is energised. What exists is the programme, the criteria and the calendar, approved in advance so that evidence accrues against a fixed standard rather than being defined after the fact. That sequencing is the point: a pass criterion written after a test is not a criterion.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled02 / 11
DRAFT
PRIMA
Commissioning & Drill ProgrammePRM-CDP-2026-001 · 03 / 11
02The gate principle — no level passed on assertion

Commissioning runs in five levels. Each is a gate, not a phase: work on the level above does not begin until the level below is signed off, and a gate is cleared by a witnessed result against a written criterion — never by a contractor's statement that a system is complete.

Written first

Every test has its acceptance criterion approved before the test is run. A result is compared against that criterion, not assessed against expectation. Where a manufacturer's tolerance and the design intent differ, the tighter of the two governs.

Criterion precedes result
Witnessed

Nothing is accepted on a report alone. Each gate names who must be physically present, and levels 4 and 5 require Prima's own engineering to witness in addition to the commissioning agent. The customer may attend L5 in full.

Presence, not paperwork
Fault-tested

A system is not proven by working. It is proven by failing safely: redundancy removed, path lost, supply cut. Levels 4 and 5 exist for this, and a system that performs perfectly under normal conditions has not passed anything.

Proven under fault
2.1 What a failed gate means

A failure is a normal and expected output of commissioning — it is the mechanism working. What is not permitted is passing it forward.

On any failed testThe result is recorded as a fail with the observed values. The test is not re-run until the cause is identified and rectified, and the rectification itself is documented.
Re-test scopeThe failed test is repeated in full, not from the point of failure. Where the fault is in a shared subsystem, every test that depends on it is repeated.
Gate statusThe gate stays closed. No level above proceeds, regardless of programme pressure. Escalation is to the COO, and only the COO may authorise a conditional pass.
Conditional passPermitted only where the open item cannot affect safety, capacity or availability, and only with a named owner and a closure date. Recorded on the gate certificate in full view — never omitted.
Procedure feedbackWhere a failure reveals that a MOP or EOP is wrong, unclear or unworkable, the procedure is revised under PRM-OPS-2026-001 before the re-test. A drill that finds a bad step triggers a technical revision, not a note.
2.2 Independence

The party that installs a system does not sign off that it works. Commissioning is directed by an independent commissioning agent appointed by Prima and reporting to the COO, not to the contractor or the EPC programme. The agent owns the scripts and the results; Prima owns the criteria and the gates.

ConsequenceBecause the agent is independent of the installer, a schedule slip is visible rather than absorbed. This is deliberate: the alternative — an installer certifying its own work under programme pressure — is the single most common origin of a facility that fails in its first year.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled03 / 11
DRAFT
PRIMA
Commissioning & Drill ProgrammePRM-CDP-2026-001 · 04 / 11
03Gate ladder — levels 1 to 3Component proving

The first three levels prove equipment in isolation: correct as built, correct as installed, correct as operating. No system interaction is tested here, and passing all three does not imply the Facility works.

LevelWhat is provenPass criterionWitness & sign-off
L1Factory witness testEach major item performs to specification before it ships — UPS modules, generators, switchgear, transformers, chillers, CDUs. Tested at the manufacturer's works under the manufacturer's own acceptance procedure, with load banks where applicable.Full compliance with the purchase specification and the manufacturer's factory acceptance procedure. Any deviation closed at the works, not on site.Commissioning agent attends in person for UPS, generators and switchgear. Prima engineering attends or joins remotely. Signed by the agent.
L2Static verificationEquipment arrived as ordered, is installed as designed, and is safe to energise. Nameplate against schedule, physical installation against drawings, cable and pipe routing, labelling, earthing, torque checks, insulation resistance, pressure test on all wet systems.100% of checklist items complete and signed. Zero open safety items. Discrepancy between as-installed and as-designed either corrected or formally accepted as a design change.Installing contractor performs; commissioning agent verifies by sample. Prima Facilities Manager countersigns.
L3Component start-upEach item works on its own once energised. First energisation, direction of rotation, protection settings and relay coordination, control response, alarm and trip points, generator start and run on load bank, UPS transfer to and from bypass, chiller and CDU run to steady state.Every measured value inside design tolerance. Every alarm and trip demonstrated to actuate at its set point — demonstrated, not calculated. Protection settings match the coordination study.Commissioning agent directs, manufacturer's engineer present for UPS, generators and chillers. Prima Facilities Manager and Engineering Manager witness. Signed by the agent, countersigned by Prima.
3.1 Sequencing against the build
L1 windowRuns against the equipment order book, ahead of shipment. Long-lead items — transformers, switchgear, generators — are tested first because a factory failure at this stage is recoverable, and one found on site is not.
L2 windowFollows each delivery and installation. Runs in parallel across disciplines; no dependency between electrical and mechanical L2.
L3 windowBegins when permanent power is available to the item being tested. Electrical L3 must complete before mechanical L3 on any plant that depends on it.
Precondition to L4All L3 certificates issued for every system in the L4 scope. A single open L3 closes the L4 gate for that system and for anything that shares it.
NoteL1 to L3 records are produced by the commissioning agent and the manufacturers. They are not authored by Prima and are not held as design documents — they are received, checked against the criteria above, and filed into the evidence pack at section 09.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled04 / 11
DRAFT
PRIMA
Commissioning & Drill ProgrammePRM-CDP-2026-001 · 05 / 11
04Gate ladder — levels 4 and 5System proving under fault

The last two levels are where availability is actually established. L4 proves each subsystem behaves correctly when a component within it fails. L5 proves the whole Facility behaves correctly when a system fails — under load, with nothing simulated on paper.

LevelWhat is provenPass criterionWitness & sign-off
L4Functional performanceEach subsystem performs as designed and rides through the loss of any single component. Automatic transfer on utility loss, generator pick-up and load acceptance, UPS on battery through the transfer, loss of one power path with A/B load retained, chiller sequencing and lead-lag rotation, CDU failover on a live loop, BMS and EPMS control response, fire detection to suppression release logic, access control fail-safe and fail-secure behaviour.Design redundancy demonstrated for every single point tested — N+1 held, 2N held where designed. IT load carried without interruption throughout. All timings inside design limits. No manual intervention where the design calls for automatic action.Commissioning agent directs. Prima Facilities Manager, Engineering Manager and Operations Manager all witness. Signed by the agent, countersigned by the COO.
L5Integrated systems testThe Facility as one system, under simulated IT load at design density, through a scripted sequence of faults and a sustained run. Full utility failure to generator and back. Black-building start from dead. Thermal ride-through across the transfer. Sequential and simultaneous plant failures. Load steps and load rejection. A continuous run at design load, including through the worst ambient window available in the test period.Cluster availability maintained across every scripted fault, thermal envelope held throughout, and the sustained run completed with zero unplanned interruptions. Measured performance consistent with the design basis, including the PUE 1.44 peak and Tier III Standard topology.Commissioning agent directs. Prima COO present throughout. Customer entitled to attend in full, on notice. Signed by the agent, the COO and the design engineer of record.
4.1 Level 5 is the admission gate

Ready for service is not a date on a programme; it is the L5 certificate. No customer load is accepted, and no availability commitment takes effect, until L5 is signed. Two consequences follow, and both are deliberate.

  • The service level does not run before L5. The 99.982% monthly cluster availability commitment under PRM-SLA-2026-001 takes effect from the date of the L5 certificate, not from first power or first login. Measuring a commitment against a facility that has not been proven would make the number meaningless.
  • The emergency procedures are drilled before L5, not after. The 17 EOPs are approved and exercised during the commissioning window — the drill calendar at section 07 is built around the L4 and L5 windows precisely because those are the only occasions when plant can be failed deliberately without a customer on it.
Not in Prima's authorshipThe L5 report is produced by the commissioning agent, not by Prima, and cannot exist before the test. This document fixes what the test must contain and what constitutes a pass — so that the report, when it arrives, is measured against a standard set in advance rather than one written around the result.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled05 / 11
DRAFT
PRIMA
Commissioning & Drill ProgrammePRM-CDP-2026-001 · 06 / 11
05Witness regime, sign-off and the documentation pack

A gate certificate is worth exactly as much as the people who signed it were present for. This section fixes who must attend, who signs, and what the customer is entitled to see.

5.1 Attendance by level
LevelMust attendSigns the certificateCustomer
L1Commissioning agent for UPS, generators, switchgear; manufacturer's test engineerCommissioning agentOn request
L2Installing contractor; commissioning agent verifying by sampleAgent + Facilities ManagerRecords only
L3Commissioning agent; manufacturer for UPS, generators, chillers; Prima Facilities and Engineering ManagersAgent, countersigned by PrimaRecords only
L4Commissioning agent; Prima Facilities, Engineering and Operations ManagersAgent, countersigned by COOOn request, may attend
L5Commissioning agent; Prima COO throughout; design engineer of record; resident shift teamAgent + COO + engineer of recordEntitled to attend in full
5.2 The resident team is present, not informed afterwards

The engineers who will hold the shift attend L4 and L5 as participants. This is the only period in the Facility's life when plant can be failed deliberately with no customer on it, and it is therefore the most valuable training that will ever be available. Attendance at L4 and L5 is recorded against each engineer's competence file under PRM-HR-2026-001 and counts toward the certification requirements named there.

5.3 The documentation pack

Each gate closes with a defined set. An incomplete pack is an open gate, irrespective of whether the tests passed.

Per testApproved script, recorded values against criteria, pass or fail, instrument calibration references, names and signatures of those present, date and time.
Per gateGate certificate listing every test in scope with its result; register of open items with owner and closure date; any conditional pass stated in full.
At L5Integrated systems test report; as-built drawings updated to reflect anything found during commissioning; final settings register for protection, control and alarm set points; approved MOP set for the commissioned plant; completed drill records per section 07.
Handover to operationsThe full pack transfers to the Operations Manager on L5 sign-off and becomes the baseline for the maintenance regime. Set points may not be changed thereafter except under change control.
RetentionHeld for the life of the asset. Commissioning records are the only proof of the design basis once the plant has been in service for years and the people who built it have moved on.
DeliberateThe customer's entitlement to attend L5 in full is stated here rather than negotiated later. A prospective offtaker who watches the facility survive a black-building start has evidence no report can substitute for — and one who is refused attendance will reasonably ask why.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled06 / 11
DRAFT
PRIMA
Commissioning & Drill ProgrammePRM-CDP-2026-001 · 07 / 11
06Drill method — how an EOP is exercised and graded17 procedures

An emergency procedure that has never been executed is an assumption. The 17 EOPs in PRM-OPS-2026-001 are exercised at three depths, and each exercise is graded against the procedure's own stated timings — not against the impression of those present.

Tabletop

The shift walks the procedure aloud against a described scenario. No plant is touched. Finds missing steps, wrong contacts, ambiguous wording and unstated assumptions. Every EOP gets one on approval, before any live exercise.

Depth 1 · no plant impact
Simulation

The condition is induced at the control or signal level — a forced alarm, an isolated sensor, a simulated trip — without failing the plant itself. Proves detection, alarm routing, escalation and the human sequence.

Depth 2 · no load impact
Live

The plant is actually failed and the procedure executed for real. The only depth that proves the procedure works. Restricted to the commissioning window and to planned maintenance windows thereafter.

Depth 3 · on load
6.1 Grading
GradeMeaningConsequence
PassExecuted as written, within every timing stated in the procedure, with no step found wrong or unclear.Recorded. Next exercise falls due per the calendar.
Pass with observationOutcome achieved, but a step was slow, awkward, or required interpretation not in the text.Editorial revision of the procedure within 20 business days. No re-exercise required.
FailOutcome not achieved, a timing missed, or the procedure could not be followed as written.Technical revision under PRM-OPS-2026-001, then re-exercise at the same depth within 30 days. Escalated to the COO.
6.2 Conduct of a live exercise
  1. Authorised in advance by the COO, with the date, scope, the plant to be failed and the abort condition stated in writing.
  2. Customer notified where the exercise falls inside a window in which the Demarcation Matrix requires notice. Once the Facility is in service, live exercises run only in agreed maintenance windows.
  3. Abort authority rests with the Shift Lead on duty, who may stop the exercise at any point without seeking approval. An aborted drill is recorded as an abort, with the reason — it is not a fail and it is not omitted.
  4. Executed by the shift on duty, not by a rehearsed team assembled for the occasion. A drill run by the best available people does not measure what will happen at 03:00.
  5. Observed and timed by the Operations Manager or a nominated deputy, against the timings in the procedure.
  6. Debriefed within 24 hours, with the record and grade filed the same week.
Restriction after service commencesCertain procedures cannot be exercised live once customer load is present — an uncontrolled EPO and a gaseous suppression release are the clear cases. From ready for service these run at simulation depth, with the release or trip inhibited at the final stage, and the fact that the last stage is inhibited is stated on the record rather than glossed.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled07 / 11
DRAFT
PRIMA
Commissioning & Drill ProgrammePRM-CDP-2026-001 · 08 / 11
07Drill calendar — to ready for serviceSep – Dec 2026

Every EOP is walked through in September, on approval of the emergency set. Live exercises are then concentrated into the L4 window in November and the L5 window in December — the only period in which plant can be failed deliberately with no customer on it. All 17 are exercised live or at simulation depth before service commences.

ReferenceProcedureSepOctNovDec
EOP — Power · 6 procedures
PRM-EOP-PWR-001Utility supply failure and generator startT·LL
PRM-EOP-PWR-002Generator fails to start on demandT·L·
PRM-EOP-PWR-003UPS on battery — load transfer and shedT·LL
PRM-EOP-PWR-004Loss of one power path, A or BT·LL
PRM-EOP-PWR-005Total loss of power — black-building recoveryTT·L
PRM-EOP-PWR-006Uncontrolled EPO activationTT·L
EOP — Cooling · 5 procedures
PRM-EOP-COL-001Chiller plant total failureT·LL
PRM-EOP-COL-002Coolant leak inside a data hallTTSL
PRM-EOP-COL-003Temperature excursion beyond the envelopeT·SL
PRM-EOP-COL-004Loss of make-up waterT·SL
PRM-EOP-COL-005Loss of secondary loop pressureT·L·
EOP — Life safety and security · 4 procedures
PRM-EOP-LSS-001Fire alarm and suppression releaseTTSS
PRM-EOP-LSS-002Water detection under floor or in hallT·SL
PRM-EOP-LSS-003Site evacuation and roll callTTLL
PRM-EOP-LSS-004Forced entry or perimeter breachTTSL
EOP — Cyber · 2 procedures
PRM-EOP-CYB-001OT network isolation on a cyber eventTTSL
PRM-EOP-CYB-002Emergency credential revocationTTSL
L — live exercise, plant actually failedS — simulation, signal level onlyT — tabletop walkthrough
7.1 Two notes on depth
  • Suppression release is never discharged. LSS-001 is exercised to the point immediately before release, with the actuator isolated — detection, cross-zoning, alarm routing, abort and evacuation are all proven; the gas is not discharged. This is standard practice and the isolation is stated on every record.
  • Black-building is run twice. PWR-005 is walked through in September and October, then run live at L5 in December from a genuinely dead facility. It is the single most demanding test in the programme and the one a lender or offtaker should ask to attend.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled08 / 11
DRAFT
PRIMA
Commissioning & Drill ProgrammePRM-CDP-2026-001 · 09 / 11
08Drill calendar — first operating year onwardRolling 12 months

From ready for service the programme becomes a rolling annual cycle. The commitment is that every one of the 17 procedures is exercised at least once in any 12-month period, spread across quarters so that no single quarter carries a disproportionate operational risk. Live depth is restricted to agreed maintenance windows.

ReferenceProcedureQ1Q2Q3Q4
EOP — Power
PRM-EOP-PWR-001Utility supply failure and generator startL··L
PRM-EOP-PWR-002Generator fails to start on demand·S··
PRM-EOP-PWR-003UPS on battery — load transfer and shedL···
PRM-EOP-PWR-004Loss of one power path, A or B·L··
PRM-EOP-PWR-005Total loss of power — black-building recovery··L·
PRM-EOP-PWR-006Uncontrolled EPO activation···S
EOP — Cooling
PRM-EOP-COL-001Chiller plant total failureL···
PRM-EOP-COL-002Coolant leak inside a data hall·S··
PRM-EOP-COL-003Temperature excursion beyond the envelope··S·
PRM-EOP-COL-004Loss of make-up water···S
PRM-EOP-COL-005Loss of secondary loop pressure·L··
EOP — Life safety and security
PRM-EOP-LSS-001Fire alarm and suppression release··S·
PRM-EOP-LSS-002Water detection under floor or in hall··S·
PRM-EOP-LSS-003Site evacuation and roll callL··L
PRM-EOP-LSS-004Forced entry or perimeter breach···L
EOP — Cyber
PRM-EOP-CYB-001OT network isolation on a cyber event··S·
PRM-EOP-CYB-002Emergency credential revocation·S··
L — live exercise, plant actually failedS — simulation, signal level onlyT — tabletop walkthrough
8.1 Rules governing the cycle
Generator on loadExercised monthly on load under PRM-MOP-ELE-004 as maintenance, independently of this calendar. The drills above test the procedure; the MOP tests the machine.
Black-buildingAnnual, in a planned window, with the customer notified under the Demarcation Matrix. The most disruptive exercise in the cycle and the one most often quietly dropped — it is scheduled in Q3 and does not move without COO authorisation.
Every shift, every yearAll four shifts participate across the annual cycle. A procedure exercised only by the day shift is not exercised — the drill record names the shift, and coverage is audited.
Unplanned events countWhere a real incident causes an EOP to be executed, that execution is recorded as an exercise and satisfies the annual requirement for that procedure, with the incident record cross-referenced under PRM-IRP-2026-001.
New or revised procedureA procedure issued at 1.0, or revised technically, is exercised at tabletop depth within 30 days of release regardless of where it sits in the calendar.
After any failRe-exercised at the same depth within 30 days, in addition to its scheduled slot. A failed drill does not consume the annual requirement.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled09 / 11
DRAFT
PRIMA
Commissioning & Drill ProgrammePRM-CDP-2026-001 · 10 / 11
09Evidence, governance and measures

The programme exists to produce a body of evidence. This section states what that evidence is, when each piece first exists, how long it is held, and how the programme itself is held to account.

9.1 What accrues, and from when
EvidenceFirst existsRetention
L1 factory acceptance certificatesPer shipmentLife of asset
L2 and L3 certificates with open-item registersPer system, on installationLife of asset
L4 functional performance reportNov 2026Life of asset
L5 integrated systems test reportDec 2026Life of asset
Drill records with grade, timings and shiftSep 2026, then continuous7 years
Final settings register — protection, control, alarmsDec 2026, then change-controlledLife of asset
As-built drawings reconciled to commissioningDec 2026Life of asset
Instrument calibration certificates for test equipmentPer test campaign7 years
9.2 Governance
Programme ownerCOO. Owns the gates, authorises live exercises and conditional passes, and is the only office that may move a scheduled drill.
Commissioning agentIndependent, appointed by Prima, reporting to the COO. Owns the scripts and results, not the criteria.
Drill executionOperations Manager. Schedules, observes, times and grades. Escalates every fail to the COO within one business day.
Competence linkageAttendance and participation are recorded against each engineer's competence file under PRM-HR-2026-001. Commissioning attendance counts toward the certification requirements named there, and a drill graded Fail is followed by targeted re-training before the re-exercise.
ReviewThe programme is reviewed annually, and after any real incident in which an EOP was executed. Review is recorded even where it results in no change, so that a current review date always exists.
© 2026 Prima Artificial Intelligence LLC · Sultanate of OmanInternal — controlled10 / 11
DRAFT
PRIMA
Commissioning & Drill ProgrammePRM-CDP-2026-001 · 11 / 11
09Evidence, governance and measures, continuedMeasures
9.3 Measures

Reported to the COO on the cadence shown, and to customers and lenders on request. A measure with no owner and no reporting interval is an intention, so each carries both.

MeasureTargetReported
EOPs exercised in the rolling 12 months100%Quarterly
Drills graded Pass or Pass with observation≥ 90%Quarterly
Shifts having participated in the annual cycle4 of 4Annually
Revisions arising from drills closed in 20 business days≥ 90%Quarterly
Scheduled drills deferred without COO authorisation0Quarterly
Gates cleared with an open conditional pass at RFS0At L5
RelatedPRM-OPS-2026-001 · PRM-IRP-2026-001 · PRM-HR-2026-001 · PRM-SLA-2026-001 · PRM-DEM-2026-001 · PRM-SEC-2026-001.
Office of the COO

For the commissioning schedule, gate certificates as issued, the drill record for any procedure, or to arrange attendance at the integrated systems test.